Example of Critical Path Analysis

This example shows the precedence network, forwards and backwards time analysis and identification of critical path for a small project.

What it does

This example shows the precedence network, forwards and backwards time analysis and identification of critical path for a small project.

See it in action

A worked example

Four tasks with their durations in days. B and C can start once A is done; D needs both. A forward pass finds the earliest times, a backward pass finds the latest. Float is the slack a task has.

Critical path for four tasks
TaskAfterDaysEarliest startEarliest finishFloat
ANone2020
BA3251
CA4260
DB and C2680

The project takes 8 days. A, C and D have no float, so they are the critical path. B can slip by one day. Links that form a loop are rejected.